Completed in March 2023.

NanoTerasu Building View past construction schedules and status reports here.

Main Building Construction

Topping-out Ceremony

Topping-out Ceremony

Held on May 19, 2021.

The ceremony celebrated the completion of the building's structural frame and prayed for the safe completion of the remaining work.

Column Setting Ceremony

Column Setting

Held on January 26, 2021.

Marked the installation of the first steel column of the main building, praying for safety during the assembly process.

Groundbreaking Ceremony

Groundbreaking Ceremony Greeting at Groundbreaking

Construction of the main building began on March 27, 2020.

On April 22, the groundbreaking ceremony was held with maximum consideration for preventing the spread of the novel coronavirus, such as strictly limiting the number of attendees and ensuring sufficient space between them.

Next-generation Synchrotron Radiation Facility Main Building Project Overview (October 2020) [PDF]

Land Development

Safety Prayer Ceremony

Safety Prayer

March 2019: Commenced land preparation.

Development work began at the Tohoku University Aobayama New Campus after obtaining all necessary permits.

Completion of Land Development

The land development work passed all inspections and was completed on November 30, 2020.

Before Construction

Before Construction (Mar 2019)

Phase 1 Completion

Phase 1 Completion (Mar 2020)

Phase 2 Completion

Phase 2 Completion (Nov 2020)

Project Overview

Period: Jan 25, 2019 – Nov 30, 2020

Contractor: Hashimoto-ten Co., Ltd.

Design/Supervision: Asia Air Survey Co., Ltd.

Site Development Development Area: 60,795m2 (Cut: 49,320m2, Fill: 11,475m2)
Earthwork Volume: 156,045m3 (Excavation: 141,630m3, Fill: 14,415m3)
Deforestation: 400 trees
Removal of Internal Roads, etc. Internal Road 7: Removed
Asphalt Pavement (t=5cm): Length 416.4m, Width 6.0m
Removal of L-shaped gutters, street catch basins, car stops, eco-tunnels
Relocation of Internal Roads Relocation of Internal Road 7
Asphalt Pavement (t=5cm): Length 448m, Width 6.0m
Installation of L-shaped gutters, street catch basins, boundary blocks
Construction of Management Roads Crushed Stone Pavement (t=20cm): Width 4.0–6.0m
Length: 435.24m
Removal of Drainage Systems Rainwater drainage pipes L=318.6m, Sewage pipes L=359.7m, Removal of 20 manholes, etc.
Restoration of Drainage Systems Rainwater drainage pipes L=295.3m, Installation of 16 manholes, 6 connecting pipes, etc.
Electrical Systems High-voltage cables, streetlights, power cables, security poles, etc.
Water Supply Systems Water supply pipes L=370.0m, Valve installation
Landscaping Turf placement: 5,413m2